Hurley - February 10, 2010
The Hurley City Council received its
monthly update covering the water and sewer projects.
The report
was completed by MSA Project Manager: Scott Martin, P.E. MSA is the
consulting firm for the engineering projects.
The monthly report
is an update of all the projects MSA is currently working on for the
City of Hurley. It summarizes the status of what has been completed on
each project in the last month and what is anticipated to be completed
in the next month.
WATER PLANT AND WELL DESIGN March 3, 2010 - April 7, 2010 Bid
Water Plant and Well Construction Bid USH 51. Watermain and
Forcemain Reconstruction The project has been advertised and
will be out to contractors to bid. The bids will be received March
third. Construction will begin as soon as weather permits. The plant and
wells should be in operation by the end of 2010.
The contractor
for the Access Road and Watermain project is A-1. Excavating, Inc.,
Bloomer, WI. Construction is substantially complete. There is some final
restoration to do next spring.
ENVIRONMENTAL FUNDING The
City received $8001000 from the Section l54 program in December. The
grant will provide 70% funding for the sanitary sewer, water and storm
sewer portion of the proposed reconstruction of Oak St, Poplar St and
Maple Street. This funding can be used in conjunction with the WDNR
funding summarized below. However coordinating the timelines for the two
funding sources will require bidding late in the summer and probably
pushing construction until 2011
WDNR SEWER AND WATER FUNDING
The City submitted an Intent to Apply for 50% grant funding for the
sanitary sewer and water portion of Oak Street, Poplar St and Maple
Street. This program is usually just a loan program but they have
unexpended stimulus funds remaining from last year and will again be
offering up to a 50% grant for projects. Last year Hurley qualified and
used a grant for the water portion of the 2009 Utility Improvement
projects. The City would not have qualified for sanitary sewer funding.
It is likely that this year's application will have the same result.
Yes, to water funding and no, to the sanitary sewer portion. This
funding can be used in conjunction with the Section l54 program
summarized above. The WDNR doesn't have a firm timeline for deciding
grant/loan awards but their rules require that funded projects be bid
before October a. Last year they announced awards in September.
Coordinating the timelines for the two funding sources will probably
result in construction being delayed until 2011
CTH D -
PRELIMINARY REVIEW The scope of the work includes preparing permit
applications, wetland delineations and soil borings in preparation of
the design of CTH D on a new alignment from STH 77 to Division Street.
The project scope of work includes construction of CTH D from
STH 77 to Division Street along a new alignment, then reconstruction of
CTH D from Division Street to USH 2. This length will be widened and
have a substantial area of marsh materials and rock excavation removed
from under the existing roadway. There will also be new sewer and water
constructed along the portion of CTH D from STH 77 to Division Street.
The water line will connect to the existing distribution system at STH
77. The sewer system will require a lift station at the intersection of
CTH D and Division Street with a forcemain constructed along Division
Street to the east that connects to the existing sewer at Tenth Avenue.
Soil borings and wetland delineation have been completed in the
proposed construct ion limits. The WDNR has requested the 240 acres
planned for development adjacent to the proposed roadway also be
delineated for the purposed of restricting future development from
impacting any wetlands identified. This delineation would be done once
the scope of the permit has been determined.
Based on our
meeting with the WDNR, it appears they will not permit the construction
of the roadway from STH 77 to Division Street thru wetlands solely to
develop the adjacent property. They believe the developable areas owned
by the City can be served by dead-end roads extended from STH 77 on the
south and Division Street on the north that will have significantly less
impact on wetlands. They will consider allowing the thru route if the
City can demonstrate a need to eliminate truck and school bus traffic
from the downtown area. MSA will contact businesses in the existing
industrial park along Odanah Road to get estimates of truck traffic
generated. We will also contact the school to get information on bus
routes to determine the impact of buses thru town. We may also look at
making some destination counts along the roadway to show a typical
number of trucks/buses during peak hours. We will submit the information
we gather to the WDNR and work with them to get the permit the City
desires.
The CTH 'D' project has been funded in the federal
budget. Congressman Obey will be in Hurley next week, Wednesday, to
make the announcement. The grant is $950,000. The City's priority is to
complete the segment of road from STH 77 to Division St. This portion of
the work is estimated to be $2,000,000. The City has also secured
$826,500 grant funding from the Section 154 program and $400,000 from
the Wisconsin Department of Commerce. This will allow the City to build
the entire project with grant funding.
|